  • EMR Working Practices

    EMR Working Practices and Guidance Documents. We will confirm which EMR Working Practices and Guidance documents we'll be launching. This will be communicated via an EMR Circular. For more information please contact us at [email protected].

  • Supplier Reserve Notices

    We’ve now issued reserve payment notices to all licensed electricity suppliers, detailing the suppliers’ reserve payment amount and the interim levy rate for the first quarterly obligation period, which covers 1 April 2015 to 30 June 2015.  Further details can be found in EMRC27, which covered the following: When did the LCCC determine the Total Reserve...

  • Registered participatants to receive further details on User Acceptance Testing

    I have registered to participate in testing, when will I receive further details? We’ll contact those Suppliers and CFD Generators who have registered to participate in UAT no later than Friday 13 March 2015 to provide further details of the scope of participating in UAT. We’ll aim to provide any details sooner if possible to...

  • Participation in User Acceptance Testing Starts

    Participation in User Acceptance Testing (UAT) for the EMR Settlement System for Suppliers and CFD Generators (who have registered interest) is scheduled to start on 23 March 2015. This aspect of UAT supports the end-to-end processes in sending invoices, credit notes and the associated backing data to participants. For more information, please see EMR Circular 33.

  • Participation in User Acceptance Testing Finishes

    Participation in User Acceptance Testing (UAT) for the EMR Settlement System for Suppliers and CFD Generators (who have registered interest) is scheduled to finish on 27 March 2015. This aspect of UAT supports the end-to-end processes in sending invoices, credit notes and the associated backing data to participants. For more information, please see EMR Circular 33.

  • EMRS System Release go-live on 1 October 2015

    On 30 September 2015, we issued EMRC60 to confirm that the EMR Settlement System Release will go-live on, 1 October 2015. The improvements made will enable the following new features: Use of the Data Transfer Network (DTN) Introduction of Energy Intensive Industries (EII) exemptions as per the Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015 Reporting of...