Posted on: 20/12/2018

On behalf of Low Carbon Contracts Company (LCCC), we’ve issued a notice to Suppliers to inform them that the Total Reserve Amount (TRA) and the Interim Levy Rate (ILR) for Quarterly Obligation Period 1 April 2019 to 30 June 2019 are as follows:

  • Total Reserve Amount is £57,089,561.02
  • Interim Levy Rate is £4.880/MWh

EMRC172 provides further information and if Suppliers are required to take any action.